Cranbrook, BC (September 9, 2024) – Phase 3 on the City’s lagoons project has officially kicked off, with the project contractor Copcan Civil LP on site and having completed the instream works and has not started on berm reconstruction. Administration provided an update on the various Capital Works projects, including the next phase of the lagoons project to Council at their regular meeting on Monday night.
Along with the removal of the debris, new riprap has been placed on the outside of lagoon three while work inside of lagoon cell two has also started. Construction of the new berm core is underway to allow re-sloping of the lagoon along the creek edge prior to riprap being placed.
Administration also updated Council on two road reconstruction projects. The 12th Avenue South reconstruction project is nearing completion with all the deep utility upgrades now in place, along with the new road structure, curb and gutter installed. Final sidewalk, road preparation and landscaping work will be completed over the next couple of weeks.
The 6th Street South reconstruction project is also close to wrapping up with all the new watermain and property services installed. The contractor is finishing the storm sewer main and catch basins and is to begin road construction over the next few days. Curb and gutter work is slated to begin around the middle of September.
An interactive, online map launched in July 2024 on the City’s website makes locations and updates on our Capital Works projects more accessible. You can find the story map and the latest information on all our Capital Works projects anytime at www.cranbrook.ca/capitalworks.